Sinton Group continues to strengthen its global service capabilities through professional on-site commissioning and technical support. Recently, Sinton successfully completed two key field debugging projects, demonstrating its engineering expertise in industrial heating systems and control optimization.
During this service trip, Sinton engineers carried out on-site commissioning for two industrial projects:
Project 1: Frame heater control cabinet debugging for an air conditioning production line in Foshan
Project 2: 80kW electromagnetic heater commissioning at Shengli Oilfield in Shandong
Both projects required precise temperature control, system stability, and seamless integration with customer-side operations.







For the Foshan project, the main objectives included:
Enabling manual and automatic control modes
Achieving local and remote control integration
Implementing PID temperature control optimization
For the Shengli Oilfield project, the focus was on:
Resolving insufficient inductance in electromagnetic coils
Supporting on-site installation and operational training
Ensuring system compliance with industrial heating standards
Through on-site debugging and system optimization, Sinton achieved excellent results:
1.Stable equipment operation across both projects
2.Temperature control accuracy improved to:
þ ±3°C for frame heater systems (better than required ±5°C)
þ ±0.1°C (pipe wall) and ±8°C (medium temperature) for electromagnetic heating systems
3.Electromagnetic coil inductance successfully adjusted to 250μH, meeting standard requirements (220–250μH)
These results highlight Sinton’s strong capability in delivering high-precision industrial heating solutions.
During commissioning, several technical issues were identified and resolved efficiently:
Solid-state relay selection mismatch in Project 1 was corrected through component replacement
PLC damage in Project 2, caused by external factors, was resolved by replacing the unit and coordinating supplier support
Sinton’s engineering team ensured minimal downtime and maintained project timelines through rapid troubleshooting and solution deployment.
Sinton emphasizes early-stage communication with on-site personnel to fully understand the equipment’s role in the production process. This ensures that debugging strategies align with real operational needs.
Engineers adjusted control parameters based on actual working conditions, including:
PID parameter tuning for temperature control systems
PLC logic modification based on site requirements
Communication protocol and address configuration for system integration
Sinton also demonstrated strong field adaptability by implementing temporary solutions when key components failed, such as:
Rewiring systems to enable short-term operation when PLC units were unavailable
Preparing contingency plans for critical component failures
This successful field commissioning project reflects Sinton’s commitment to:
Delivering reliable and energy-efficient heating solutions
Providing professional on-site technical services
Supporting customers with end-to-end engineering expertise
With over 20 years of experience in industrial heating systems, Sinton continues to serve global clients across HVAC, oil & gas, and manufacturing industries.
Looking For Business Opportunity?
Request for a call today
WhatsApp: +86-185-5601-8866
Tel: +86-185-5601-8866
E-mail: [email protected]
Address: Sinton Building, No. 886 Yandu Road, Yandu District, Yancheng City, Jiangsu Province
Friendly Link: www.cn-lvdao.com www.sealing-china.com
Products
Message